Viracopos Airport (SBKP/VCP)
Published in
Jul 07, 2021 11:59 AM
Updated in
Jul 07, 2021 03:08 PM
Viracopos Airport (SBKP/VCP) was granted to the private initiative in an auction held on BM&BOVESPA on February 6th, 2012.
Concessionaire: Aeroportos Brasil Viracopos
Website: http://www.viracopos.com/
Concession object: Concession of the public services for the expansion, maintenance and exploration of the infrastructure of the airport complex.
Date of contract signature: June 14th, 2012
Start of concession: July 11th, 2012
Concession term: 30 years
Bidding Process
INFORMATION ABOUT THE BIDDING PROCESS: BRASÍLIA (SBBR/BSB), CAMPINAS (SBKP/VCP) AND GUARULHOS (SBGR/GRU) - available only in PortugueseInvestments and works
- June 14th, 2012 – Concession contract signature
- July 11th, 2012 – Effective date of contract
- February 14th, 2013 – End of Phase IA. Transfer of operations from the Brazilian Airport Infrastructure Company (Infraero) to the concessionaire
- May 11th, 2014 – End of Phase IB. Delivery of mandatory investments:
- Passenger terminal with capacity to simultaneously process 1,550 boarding and 1,550 arriving passengers
- Patio for 35 aircrafts, with 28 parking positions to be served by boarding bridges
- Access roads and parking lot with 4,500 spaces
- Obstacle removal and providing of graded area of runway and taxiways strips, according to the critical operation for airplanes which the runway and taxiways are intended to serve
- May 12th, 2014 – Start of Phase IC. Recovery of service level
- May 12th, 2016 – End of Phase IC. Recovery of service level
- May 13th, 2016 – Start of Phase II
- Maintenance of service level
- Investment triggers
- December 31st, 2018 – Delivery of mandatory investments:
- Implementation of new runway end safety areas
- 178.000 mov. / year demand or end of Phase II – Delivery of mandatory investments:
- Construction of second runway, with 3,600m length.
- 351.000 mov. / year demand or end of Phase II – Delivery of mandatory investments:
- Construction of third runway, with 2,600m length.
- Reaching 456.000 mov. / year – Delivery of mandatory investments:
- Construction of fourth runway, with 2,200m length
- July 11th, 2042 – End of Phase II
Related Documents
- Contrato de concessão (available only in Portuguese)
- Termos aditivos (available only in Portuguese)
- Ordem de serviço (available only in Portuguese)
- Reajuste de tarifas (available only in Portuguese)
- Indicadores de Qualidade de Serviço (available only in Portuguese)
- Contratos com partes relacionadas (available only in Portuguese)
- Extrato dos contratos de concessão (publicação DOU) - available only in Portuguese
- Demonstrações financeiras (available only in Portuguese)
- Documentos anteriores à audiência pública (available only in Portuguese)
- Plano Amostral e Voos extras (available only in Portuguese)