Galeão Airport (SBGL/GIG)
Published in
Jul 07, 2021 11:38 AM
Updated in
Jul 07, 2021 02:52 PM
Galeão Airport (SBGL/GIG) was granted to the private initiative in an auction held on BM&BOVESPA on November 22nd, 2013.
Concessionaire: RIOgaleão
Website: http://www.riogaleao.com/
Concession object: Concession of the public services for the expansion, maintenance and exploration of the infrastructure of the airport complex.
Date of contract signature: April 2nd, 2014
Start of concession: May 7th, 2014
Concession term: 25 years
Bidding Process
INFORMATION ABOUT THE BIDDING PROCESS: GALEÃO (SBGL/GIG) AND CONFINS (SBCF/CNF) - available only in PortugueseInvestments and works
- April 2nd, 2014 – Concession contract signature
- May 7th, 2014 – Effective date of contract
- December 31st, 2014 – Delivery of mandatory investments:
- Implementation of runway end safety areas
- February 2nd, 2015 – End of Phase IA. Transfer of operations from the Brazilian Airport Infrastructure Company (Infraero) to the concessionaire.
- December 31st, 2015 – Delivery of mandatory investments:
- Adequacy of runways systems for F-Code aircrafts
- Access roads and parking lots with minimum 1,850 additional spaces
- April 30th, 2016 – Start of Phase IB. Delivery of mandatory investments and recovery of service level
- Expansion of passenger terminal with 26 additional boarding bridges
- Patio for 97 aircrafts
- May 1st, 2016 – Start of Phase II
- Maintenance of service level
- Investment triggers
- Rio 2016 Summer Olympic Games. Delivery of mandatory investments:
- Adequacy of facilities for cargo storage in compliance with the commitments made to the International Olympic Committee
- December 31st, 2016 – Delivery of mandatory investments:
- Obstacle removal and providing of graded area of runway and taxiways strips, according to the critical operation for airplanes which the runway and taxiways are intended to serve
- December 31st, 2018 - Delivery of mandatory investments:
- Implementation of runway end safety areas
- 262.900 mov. / year demand – Delivery of mandatory investments:
- Landing and takeoff runway, with 3,000m length, for E-Code aircrafts.
- May 7th, 2039 – End of Phase II.
Related Documents
- Contrato de concessão (available only in Portuguese)
- Termos aditivos (available only in Portuguese)
- Ordem de serviço (available only in Portuguese)
- Reajuste de tarifas (available only in Portuguese)
- Indicadores de Qualidade de Serviço (available only in Portuguese)
- Contratos com partes relacionadas (available only in Portuguese)
- Extrato dos contratos de concessão (publicação DOU) - available only in Portuguese
- Demonstrações Financeiras (available only in Portuguese)
- Dados dos Indicadores de Qualidade de Serviço (available only in Portuguese)
- Plano Amostral e Voos extras (available only in Portuguese)